Softball Field Construction Update
Many changes have taken place since last spring to create the new Sutton Softball Field. Here are recent images of the progress.
The lights are installed, the parking lots are paved, the dugouts are constructed, the concrete pads for the bleachers and batting cage are completed, the poles for the fence are set, and the irrigation system is installed. Over the next several weeks, the drainage system will be completed, the fencing finished and finally the sod will be installed. Sutton Softball Field is scheduled for completion on September 1, 2008.